Week Commencing 7th March 2022

Colonnade / Ground Floor:

  • Groundworks in Colonnade
  • Installing steelwork on retail units
  • Installing supporting steelwork for stonework
  • Stonework cladding to Colonnade
  • Removal of floor finishes for Scenic Lifts in Central Square
  • Steel erection for Scenic Lifts in Central Square
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • MEP services installation in 123 loading bay + mezz areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • Steel frame erection
  • Metal decking and rebar for new concrete floors
  • Pouring concrete floors
  • Roofing works on Level 8
  • 123 Type H Central Square curtain walling installation

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof

Expected impact to Building Neighbours:

  • Low level construction noise during the day
  • Medium level noise during Noisy Works Period

Week Commencing 14th March 2022

Colonnade / Ground Floor:

  • Groundworks in Colonnade
  • Installing steelwork on retail units
  • Installing supporting steelwork for stonework
  • Stonework cladding to Colonnade
  • Steel erection for Scenic Lifts in Central Square
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • Steel frame erection
  • Metal decking and rebar for new concrete floors
  • Pouring concrete floors
  • Roofing works on Level 8
  • 123 Type H Central Square curtain walling installation

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof

Expected impact to Building Neighbours:

  • Low level construction noise during the day
  • Medium level noise during Noisy Works Period

Week Commencing 21st March 2022

Colonnade / Ground Floor:

  • Groundworks in Colonnade
  • Installing steelwork on retail units
  • Installing supporting steelwork for stonework
  • Stonework cladding to Colonnade
  • Steel erection for Scenic Lifts in Central Square
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • Steel frame erection
  • Metal decking and rebar for new concrete floors
  • Pouring concrete floors
  • Roofing works on Level 8
  • 123 Type H Central Square curtain walling installation
  • 123 & 151 Installation of Sky Lobby Curtain Walling

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof

Expected impact to Building Neighbours:

  • Low level construction noise during the day
  • Medium level noise during Noisy Works Period

Week Commencing 28th March 2022

Colonnade / Ground Floor:

  • Groundworks in Colonnade
  • Installing steelwork on retail units
  • Installing supporting steelwork for stonework
  • Stonework cladding to Colonnade
  • Steel erection for Scenic Lifts in Central Square
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • Steel frame erection
  • Metal decking and rebar for new concrete floors
  • Pouring concrete floors
  • Roofing works on Level 8
  • 123 Type H Central Square curtain walling installation
  • 123 & 151 Installation of Sky Lobby Curtain Walling
  • MEP packaged plant and services installation

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof

Expected impact to Building Neighbours:

  • Low level construction noise during the day
  • Medium level noise during Noisy Works Period