Week Commencing 2nd May 2022
Colonnade / Ground Floor:
- Groundworks in Colonnade
- Installing steelwork on retail units
- Stonework cladding to Colonnade
- Steel erection for Scenic Lifts in Central Square
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- Metal decking and rebar for new concrete floors
- Roofing works on Level 8
- Removing stair overruns for staircore extensions
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1 & 2
Expected impact to Building Neighbours:
- Low level construction noise during the day
- Medium level noise during Noisy Works Period
Week Commencing 9th May 2022
Colonnade / Ground Floor:
- Groundworks in Colonnade
- Installing steelwork on retail units
- Stonework cladding to Colonnade
- Steel erection for Scenic Lifts in Central Square
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- Metal decking, rebar and concreting for new floors
- Roofing works on Level 8
- Removing stair overruns for staircore extensions
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1 & 2
Expected impact to Building Neighbours:
- Low level construction noise during the day
- Medium level noise during Noisy Works Period
Week Commencing 16th May 2022
Colonnade / Ground Floor:
- Groundworks in Colonnade
- Installing steelwork on retail units
- Stonework cladding to Colonnade
- Steel erection for Scenic Lifts in Central Square
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- Metal decking, rebar and concreting for new floors
- Roofing works on Level 8
- Removing stair overruns for staircore extensions
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1 & 2
Expected impact to Building Neighbours:
- Low level construction noise during the day
- Medium level noise during Noisy Works Period
Week Commencing 23rd May 2022
Colonnade / Ground Floor:
- Groundworks in Colonnade
- Installing steelwork on retail units
- Stonework cladding to Colonnade
- Steel erection for Scenic Lifts in Central Square
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- Concreting for new floors
- Roofing works on Level 8
- Removing stair overruns for staircore extensions
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1, 2 & 3
Expected impact to Building Neighbours:
- Low level construction noise during the day
- Medium level noise during Noisy Works Period
Week Commencing 30th May 2022
Colonnade / Ground Floor:
- Groundworks in Colonnade
- Installing steelwork on retail units
- Stonework cladding to Colonnade
- Steel erection for Scenic Lifts in Central Square
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- Concreting for new floors
- Roofing works on Level 8
- Removing stair overruns for staircore extensions
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1, 2 & 3
Expected impact to Building Neighbours:
- Low level construction noise during the day
- Medium level noise during Noisy Works Period