Week Commencing 6th June 2022

Colonnade / Ground Floor:

  • Installing glazing on retail units
  • Stonework cladding to Colonnade
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • Concreting for new floors
  • ETFE Roof stubs and steelwork
  • 123 Type H Central Square curtain walling installation
  • 123 & 151 Installation of Sky Lobby Curtain Walling
  • MEP packaged plant and services installation

Cores / Plantrooms:

  • Core 2 staircore lighting
  • Existing sprinkler pump changeover works
  • Google Core 1 ground floor containment works

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof
  • Cladding operatives working outside Levels 1, 2 & 3

Week Commencing 13th June 2022

Colonnade / Ground Floor:

  • Installing glazing on retail units
  • Stonework cladding to Colonnade
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • Concreting for new floors
  • ETFE Roof stubs and steelwork
  • 123 Type H Central Square curtain walling installation
  • 123 & 151 Installation of Sky Lobby Curtain Walling
  • MEP packaged plant and services installation

Cores / Plantrooms:

  • Core 2 staircore lighting
  • Existing sprinkler pump changeover works
  • Google Core 1 ground floor containment works

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof
  • Cladding operatives working outside Levels 1, 2 & 3

Week Commencing 20th June 2022

Colonnade / Ground Floor:

  • Installing glazing on retail units
  • Stonework cladding to Colonnade
  • Strip out of retail units in Fountain Square
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • ETFE Roof stubs and steelwork
  • 123 Type H Central Square curtain walling installation
  • 123 & 151 Installation of Sky Lobby Curtain Walling
  • MEP packaged plant and services installation

Cores / Plantrooms:

  • Existing sprinkler pump changeover works
  • Google Core 2 ground floor containment works

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof
  • Cladding operatives working outside Levels 1, 2 & 3

Week Commencing 27th June 2022

Colonnade / Ground Floor:

  • Installing glazing on retail units
  • Stonework cladding to Colonnade
  • Strip out of retail units in Fountain Square
  • Installation of Type J Retail Facades
  • MEP services installation in 123 retail areas
  • Installation of Type G Rainscreen Cladding
  • 123BPR Reception Refurbishment

Roof Levels 6-8:

  • ETFE Roof stubs and steelwork
  • 123 Type H Central Square curtain walling installation
  • 123 & 151 Installation of Sky Lobby Curtain Walling
  • MEP packaged plant and services installation

Cores / Plantrooms:

  • Existing sprinkler pump changeover works
  • Google Core 2 ground floor containment works

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof
  • Cladding operatives working outside Levels 1, 2 & 3