Week Commencing 6th June 2022
Colonnade / Ground Floor:
- Installing glazing on retail units
- Stonework cladding to Colonnade
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- Concreting for new floors
- ETFE Roof stubs and steelwork
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Cores / Plantrooms:
- Core 2 staircore lighting
- Existing sprinkler pump changeover works
- Google Core 1 ground floor containment works
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1, 2 & 3
Week Commencing 13th June 2022
Colonnade / Ground Floor:
- Installing glazing on retail units
- Stonework cladding to Colonnade
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- Concreting for new floors
- ETFE Roof stubs and steelwork
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Cores / Plantrooms:
- Core 2 staircore lighting
- Existing sprinkler pump changeover works
- Google Core 1 ground floor containment works
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1, 2 & 3
Week Commencing 20th June 2022
Colonnade / Ground Floor:
- Installing glazing on retail units
- Stonework cladding to Colonnade
- Strip out of retail units in Fountain Square
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- ETFE Roof stubs and steelwork
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Cores / Plantrooms:
- Existing sprinkler pump changeover works
- Google Core 2 ground floor containment works
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1, 2 & 3
Week Commencing 27th June 2022
Colonnade / Ground Floor:
- Installing glazing on retail units
- Stonework cladding to Colonnade
- Strip out of retail units in Fountain Square
- Installation of Type J Retail Facades
- MEP services installation in 123 retail areas
- Installation of Type G Rainscreen Cladding
- 123BPR Reception Refurbishment
Roof Levels 6-8:
- ETFE Roof stubs and steelwork
- 123 Type H Central Square curtain walling installation
- 123 & 151 Installation of Sky Lobby Curtain Walling
- MEP packaged plant and services installation
Cores / Plantrooms:
- Existing sprinkler pump changeover works
- Google Core 2 ground floor containment works
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1, 2 & 3