Week Commencing 1st August 2022
Colonnade / Ground Floor:
- Installing glazing on retail units
- Stonework cladding to Colonnade
- Strip out of retail units in Fountain Square
- Installation of rainscreen cladding on Colonnade
- MEP services installation in 123 retail areas
- 123BPR Reception Refurbishment
- New staircases and ramps on Ecclestone Bridge
Roof Levels 6-8:
- ETFE Roof installation
- 123 & 151 Installation of Sky Lobby curtain walling
- MEP packaged plant and services installation
- Toilet blocks in Cores
- Lift extensions in Cores 2 & 7
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof
- Cladding operatives working outside Levels 1, 2 & 3
Week Commencing 8th August 2022
Colonnade / Ground Floor:
- Installing glazing on retail units
- Stonework cladding to Colonnade
- Strip out of retail units in Fountain Square
- Installation of rainscreen cladding on Colonnade
- MEP services installation in 123 retail areas
- 123BPR Reception Refurbishment
- New staircases and ramps on Ecclestone Bridge
Roof Levels 6-8:
- ETFE Roof installation
- 123 & 151 Installation of Sky Lobby curtain walling
- MEP packaged plant and services installation
- Toilet blocks in Cores
- Lift extensions in Cores 2 & 7
Expected impact to Building Residents:
- High level noise during agreed Noisy Works Periods
- Medium level noise in the Colonnade and Roof