Week Commencing 1st August 2022

Colonnade / Ground Floor:

  • Installing glazing on retail units
  • Stonework cladding to Colonnade
  • Strip out of retail units in Fountain Square
  • Installation of rainscreen cladding on Colonnade
  • MEP services installation in 123 retail areas
  • 123BPR Reception Refurbishment
  • New staircases and ramps on Ecclestone Bridge

Roof Levels 6-8:

  • ETFE Roof installation
  • 123 & 151 Installation of Sky Lobby curtain walling
  • MEP packaged plant and services installation
  • Toilet blocks in Cores
  • Lift extensions in Cores 2 & 7

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof
  • Cladding operatives working outside Levels 1, 2 & 3

Week Commencing 8th August 2022

Colonnade / Ground Floor:

  • Installing glazing on retail units
  • Stonework cladding to Colonnade
  • Strip out of retail units in Fountain Square
  • Installation of rainscreen cladding on Colonnade
  • MEP services installation in 123 retail areas
  • 123BPR Reception Refurbishment
  • New staircases and ramps on Ecclestone Bridge

Roof Levels 6-8:

  • ETFE Roof installation
  • 123 & 151 Installation of Sky Lobby curtain walling
  • MEP packaged plant and services installation
  • Toilet blocks in Cores
  • Lift extensions in Cores 2 & 7

Expected impact to Building Residents:

  • High level noise during agreed Noisy Works Periods
  • Medium level noise in the Colonnade and Roof