The Central Square glass curtain walling and rainscreen cladding on 151 & 123 Levels 1 & 2 is continuing.
The Retail Unit glazing on Ecclestone Bridge is now complete. They are now installing glazing on the Colonnade on 123.
The steel frame for the new ETFE Roof is now complete and the “pillows” will start going in next week.
Our new site entrance is now on Ecclestone Bridge. The Out of Hours Entrance is still in the same place and is unaffected by this change.
Please be aware that we will removing our Tower Crane TC1 on the weekend of 18th/19th June 2022. Buckingham Palace Road will be closed in front of 123-151BPR from late evening on Friday, 17th June
until 6am on Monday, 20th June.